The Minister of Works and Transport, Hon. Fred Byamukama, on 13 November, 2026 concluded a two-day inspection of road projects in the Tooro and Rwenzori sub-regions, assessing ongoing works and engaging local leaders on road safety, connectivity and infrastructure needs.
On the final day, the Minister inspected the Fort Portal–Kasese–Kikorongo Road (90km) and ongoing rehabilitation works on the Kikorongo–Bwera–Mpondwe Road (38.2km), undertaken by Dott Services Limited. The inspection focused on progress of works, road safety and concerns raised by local leaders regarding sections along the cross-border corridor.

Ongoing rehabilitation works on the Kikorongo–Bwera–Mpondwe Road (38.2km)
Hon. Byamukama noted that increasing heavy goods traffic, particularly trucks transporting cargo between Uganda and the Democratic Republic of Congo (DRC), had contributed to the deterioration of the Kikorongo–Bwera–Mpondwe Road. He acknowledged delays on the project but said the contractor had mobilised and was accelerating works.
The UGX 105.35 billion project, funded by the Government of Uganda, involves upgrading the 38.2km road through widening, improved drainage, culverts, asphalt concrete surfacing, climbing lanes and urban facilities, including walkways and parking lanes in Mpondwe. The Minister assured the public that the upgraded road would accommodate heavy traffic and serve for an estimated 15 years before requiring periodic maintenance.
He urged road users and surrounding communities to exercise patience and observe safety precautions during construction. He also reiterated Government’s commitment to completing ongoing road projects before embarking on new ones.
The Minister raised concerns about the location of the existing One-Stop Border Post, approximately 500 metres from the main road, noting that this creates challenges for tax collection and public health surveillance. He proposed redesigning the border crossing to accommodate a new One-Stop Border Post and Health facility closer to the main road. He committed to engaging the Ministers responsible for Trade and Internal Affairs and other stakeholders to explore possible improvements.
The inspection was attended by Hon. Dr. Julius Monday Rude, Member of Parliament for Bukonzo County East, and Hon. Sowedi Kitanywa, Member of Parliament for Busongora County North, Kasese District. The legislators welcomed the visit and requested that the sections of Mpondwe–Bwera Hospital access, Kiburara–Kagando–Kisinga and Mpondwe–Lhubiriha be considered for inclusion in the ongoing works.
Hon. Kitanywa urged residents to use the improved road infrastructure to support trade and socio-economic transformation.Meanwhile, Lt. Abel Nyomayondi, Mayor of Rwimi Town Council, appealed to the Ministry to address a steep gradient along the Kasunganyanja–Rwimi section of the Fort Portal–Kasese Road, which he said had contributed to accidents.
In his response, the Minister pledged to engage the Ministry’s technical team to assess the section and explore possible redesign solutions to improve safety.