Kyenjojo-Kabwoya Road (100 km)
Project Details |
Information |
Project name and Length |
Civil works for the Upgrading of Kyenjojo – Kabwoya Road (100.4km) from gravel to paved (Bitumen) Standard |
Contractor |
Shengli Engineering Construction (Group) Co. Ltd of Shengli Oilfield, China |
Contract sum |
UGX447,605,516 and USD3,079,482 |
Funder (s) |
The World Bank / Government of Uganda |
Districts traversed by project |
Kyenjojo, Kagadi and Kikuube |
Commencement date |
5th April 2016 |
Completion date |
Original: 4th April 2019. Revised:15th October 2019 (awaiting World bank No-Objection) |
Work done to date |
67.85% against 71.88% of planned |
Supervision Consultant |
M/s. Comptran Engineering & Planning Associates, Ghana |
Supervision commencement |
5th April,2016 |
Supervision sum |
USD 2,824,521 |
Sub-Contractor (Electricity) |
M/s. Mantab |
Sub-Contractor (Water) |
M/s. Cribb Technical Services Ltd, Uganda |
The total length of the road is 100.4km constructed by M/s. Shengli Engineering Construction (Group) Co. Ltd of Shengli Oilfield and being supervised by M/s. Comptran Engineering Construction and Planning Associates (Ghana). The project road traverses the three districts of Kyenjojo, Kagadi and Kikuube. The work commenced on 5th April 2016 for duration of 36 months. The revised completion date awaiting World Bank No objection is 15th October 2019. The works contract amount is UGX 214,563,989,426 while the supervision contract amount is USD 2,824,521.
The carriageway and shoulders will be sealed with Double Bituminous Surface Treatment (DBST) wearing course. The project has subcontractors i.e. M/s MANTAB for relocating electricity and M/s Cribb Technical Services Ltd, Uganda for relocating water. M/s Community Health Promotion Consultants (COHEPCO) Uganda was the nominated service provider for HIV/AIDS and BRAC Uganda is the nominated service provider for GBV/VAC
Project progress
Actual physical works as of July 2019 was at 67% against a planned 71%. In terms of time, the project has used 40 months out of the 45months but the original project length was 36 months.
Buhimba-Nalweyo-Bulamagi&Bulamagi-Igayaza-Kakumiro (93km)
Project detail |
Information |
Project Title: |
Design and Build of Buhima-Nalweyo-Bulamagi and Bulamagi-Igayaza-Kakumiro Roads (93km) |
Funded by: |
Loan funds obtained from China Exim Bank |
Engineer: |
Kagga &Partners Ltd |
Contractor: |
M/s. China Wu Yi Co. Ltd |
Consultant: |
UNRA supervision team |
Original Contract Price: |
USD. 138,488,356 |
Commencement date: |
13th April 2018 |
Construction period: |
1099 days (36 months) |
Completion date: |
16th April 2021 |
Project details
The Government of the Republic of Uganda applied for a loan from China Exim Bank and contracted M/s. China Wu Yi Co. Ltd at a sum of USD. 138,488,356 to Design and Build Buhimba-Nalweyo-Bulamagi and Bulamagi-Igayaza-Kakumiro Roads (93km). The works include all field works, detailed engineering and construction of 93km of roads.
Scope of works
The Buhimba-Nalweyo-Bulamagi and Bulamagi-Igayaza-Kakumiro road will be upgraded to Class II (bituminous) standard with a 7-meter wide carriageway and 2.0-meter wide shoulders on both sides of the carriageway. The existing road has an average existing carriage way width of 4.5m with a drain to drain with of 7.5m.
Progress
Cumulative physical progress at end of July is 16.3% against planned cumulative progress of 26%, giving a slippage of 9.7%. Cumulative financial progress at end of July was 27.0% against 34.0% planned. Time progress at the end of July was 474 days (43% of Contract Period). The progress of the Contractor is being tracked based on the revised program of works.
Hoima-Butiaba-Wanseko (111km)
Project detail |
Information |
Project name |
Civil works for upgrading of Hoima-Butiaba- Wanseko road from gravel to paved (Bituminous Standard 111km) |
Implementing Agency |
UNRA |
Employer |
GoU represented by UNRA |
Funding Agency |
GoU and EXIM Bank of China |
Contractor |
Chongqing International Construction Corporation (CICO) Ltd |
UNRA Project Management team |
Project Manager: Alfred Tugume Kahonaho Project Engineer: Rogers Ssentongo |
Supervising Engineer |
UNRA construction and supervisoion Team Engineer: Eng: Samuel Muhoozi Resident Engineer: Eng. Ronald Olaki |
Contract Amount |
USD 179,538,545.59 |
Contract signature date |
18th January 2018 |
Commencement date |
16th April 2018 |
Original completion date |
A6th April 2021 |
Original project duration |
36months |
Time completed to date |
14.5 months (40.3%) |
Defects Liability period |
12 Months |
Project details
Government together with the oil partners identified critical oils roads that must be upgraded by the prescribed time in order to achieve the 2020 target. Because of this, the GOU through MoFPED applied for financing support from China Exim Bank to fund the construction of Hoima-Butiaba-Wanseko road (111km) for upgrading to bituminous standard from gravel. Chongqing International Construction Corporation (CICO) Ltd the contractor is expected to deliver 30% of the road made up of continuous road section as proposed by the contractor (0+000) to (37+000) including all the bridges within 58% of the contract time and the remaining works of the project after 36months from the commencement date of 16th April 2018.
The main objective of the project are to;
- Improve the road infrastructure within the mineral and oil exploration zones which are in both Hoima and Bulisa districts
- Improve access to social and economic development opportunities along the route and integration to the rest of the rest of the country by providing high capacity infrastructure
- Ensure that no road side communities become worse off as a result of the road upgrading work
Progress
Cumulative physical progress of civil works was at 30% against a planned 27%. Financial progress stood at 27% against a planned 32%. In terms of time, the project 40%.
Masindi Park Junction and Tangi Junction-Para-Bulisa Roads (159km)
Project Details |
Information |
Project name and Length |
Civil Works for Design and Build for Upgrading from Gravel to Paved Standard of Masindi (Kisanja) - Park Junction and Tangi Junction - Paraa - Buliisa (159 Km) |
Contractor |
China Communications Construction Company Ltd. (CCCC) |
Supervision consultant |
Abuljebain Engineering Consulting Office (AECO) in association with Technology Consult Ltd |
Contract sum |
USD 218,888,518.4 |
Funder (s) |
China Exim Bank and Government of Uganda |
Scope of Works |
Design and Build Contract |
Surfacing |
Asphalt Concrete |
Commencement date |
23rd April 2018 |
Completion date |
26th April 2021 |
Contract time elapsed |
44.22% |
Physical Progress |
11.36% against 43.18% |
Design Progress |
86.57% against the planned 100.00% |
Contractor’s staff |
822 Staff (Male: 756, Female: 66; 671 Local, 151 Foreign) |
Supervisor’s staff |
27 Staff (21 Males, 6 Females; 26 Local, 1 Foreign) |
Project details
This project is located in Western Uganda and crosses the districts of Masindi, Nwoya and Buliisa. The road traverses a flat/rolling terrain and it involves upgrade of the road to bituminous paved road. The project consists of four lots namely;
- Masindi – Kisanja (72 km)
- Sambiya – Murchison Falls (12 km)
- Tangi Junction – Paraa – Buliisa (52 km)
- Wanseko – Bugungu (23 km)
Project Scope
The scope of work consists of:
- Widening the embankment, bush clearing and topsoil stripping. The lower subgrade is made of G7 fill materials of 250-350 mm and the improved subgrade of G15 125-350mm. The subbase will be chemically stabilized cement of 150-215 mm, 125-150 mm of crushed stone base course and a wearing course of Asphalt Concrete of 55-100mm.
- Installation of concrete pipe culverts of 900 mm and 1200mm and construction of single and multiple cell box culverts.
- Construction of a total of 7 bridges along the road, and these include four (4) along Masindi – Kisanja section namely; Waiga with a span of 24m, Wairongo with a span of 30m, Zoliya with a span of 18m, and Sambiya with a span of 18m.
Three (3) bridges are on Tangi Junction – Paraa – Buliisa section namely; Tangi with a span of 30m, Emmi with a span of 18m and a big Paraa Bridge with a span of 525m.
- Paraa bridge, which is composed of 13 spans each at 40m and bridge deck of 15.95m wide.
Project progress
- The work done against progress stands at 11.36% against a planned 43.18% indicating slippage of 31.82%.
- The design progress stands at 86.57% against a planned 100.00% indicating slippage of 13.43%.
- The financial progress is 13.78% against a planned 45.42%.
- The contract time elapsed by the time of the visit was 44%.
- Works on the bridges stands at Waiga 39.67%, Wairongo 54.10%, Zoliya 43.05%, Sambiya 22.76%, Tangi the designs had just been approved, Emmi 18.17% and Paraa Bridge 9.55% and a temporary steel bridge had been completed and use.
USMID Roads in Gulu
Project details
The objective of the Uganda Support to Municipal Infrastructure Development Program Project (USMID) is to enhance the institutional performance of program Municipal Councils (MCs) to improve urban service delivery.
The program will also involve a range of administration, oversight and support activities to be undertaken by the relevant central government entities responsible for the various elements of the implementation of the Program. The main aim of the program is to enhance the capacity of the targeted municipalities to improve urban service delivery in the context of a rapidly urbanizing society in which significant service delivery responsibilities have been decentralized.
The Overall Program Objective is to enhance the institutional performance of the 14 Municipal Councils to improve urban service delivery. The participating Municipal Councils (MCs) are; Arua, Lira, Gulu, Soroti, Entebbe, Mbale, Tororo, Jinja, Masaka, Hoima, Fort portal, Mbarara, Kabale and Moroto.
Under the entire USMID project, Infrastructure construction provided direct employment to 2,716 people of which 442 were female representing 16.3% of the entire workforce. The project has also improved 66,113 square meters of green area and planted 2,407 trees.
The Project
Gulu Municipality as one of the 14 recipients of the infrastructure development grant under the World Bank funded Uganda Support to Municipal Infrastructure Development (USMID). It is believed that through this improved road network, transacting business with neighboring districts as well as South Sudan will greatly improve thus leading to transformation of livelihoods.
The project requires upgrading the roads from gravel surface road to an Asphalt surface layer of 50mm, with base course and sub-base layers. A carriage way of 7 m total width with two lanes in opposite direction, a parking lane each side, a cycle lane on each side, 1.5m walkways on each side of the road, street lights, service ducts and drains. Gulu has since rehabilitated and tarmacked roads that include:
Completed USMID Projects Phase 1A
S/No |
Road Name |
Length (km) |
Lanes |
1 |
Labor Line Road |
0.331 |
2 |
2 |
Cemetery Road |
0.408 |
2 |
3 |
Acholi Lane |
0.608 |
2 |
4 |
Alokolum Road |
0.651 |
2 |
5 |
Ring Road |
1.64 |
4 |
TOTAL |
3.638 |
Completed USMID Projects Phase 1B
S/No |
Road Name |
Distance (Km) |
Lanes |
01 |
Kabalega Road |
0.160 |
2 |
02 |
Adonga Road |
0.334 |
2 |
03 |
Crane Avenue |
0.195 |
2 |
04 |
Philip Tarner |
0.266 |
2 |
05 |
Odur Min Odyek Rd |
0.336 |
2 |
06 |
Commercial road |
0.364 |
2 |
07 |
School Road |
0.355 |
2 |
08 |
Salvatore Olwochi Road |
0.672 |
2 |
09 |
Oponya Walter Road |
0.670 |
4 |
10 |
Muroni Road |
0.694 |
2 |
11 |
Lumumba Avenue |
0.250 |
4 |
12 |
Lango Road |
0.226 |
2 |
TOTAL |
4.522 |
BATCH II 2017-2018
S/No |
Activity Name |
Distance (km) |
Lanes |
01 |
Preliminaries |
||
02 |
Laroo road |
2.46 |
2 |
03 |
Alex Ojera road |
0.680 |
2 |
04 |
Tank road |
0.340 |
2 |
05 |
Dr. Kenneth Onekalit road |
0.270 |
2 |
06 |
Lasto Okech road |
0.500 |
2 |
07 |
Golf-Course road |
0.450 |
2 |
08 |
Nyerere Avenue |
0.880 |
2 |
09 |
Odida road |
0.250 |
2 |
10 |
Timothy Okwera road |
0.420 |
2 |
11 |
Peter Paul Opok road |
0.860 |
2 |
12 |
Bro. Reuben road |
0.640 |
2 |
13 |
Sir Samuel Baker road |
1.280 |
2 |
14 |
Hussan Mitchel road |
0.540 |
2 |
TOTAL |
9.37 |
Olwiyo-Gulu Road(70.3km)
Project Detail |
Information |
Project name and Length |
Civil Works for the Upgrading of Olwiyo - Gulu Road (70.3 Km) from Gravel to Paved (Bituminous) Standard. |
Contractor |
M/S Zhongmei Engineering Group Ltd. |
Previous Supervision Consultant |
M/S Comptran Engineering and Planning Associates |
Current Supervision Consultant |
UNRA In-House Supervision Team (Since 2nd June 2019) |
Contract sum |
UGX 164,025,932,344 |
Funder (s) |
Government of Uganda |
Commencement date |
18th September 2014 |
Original Completion date |
21st September 2017 revised to 4th December 2019 |
Period of Contract time elapsed |
94.30% (According to revised Completion Date) |
Work done to date |
95.12% as of August 2019 |
Contractor’s staff |
376 staff (male: 342, female: 34; 308 local and 34 foreign) |
Supervisor’s staff |
23 staff (20 males, 3 female; 15 local, 8 foreign) |
Project Details
This project aims at upgrading of Olwiyo - Gulu road (70.3km) to class II Standard paved road with a double bituminous surface dressed carriageway of 20mm thick and 7m width. The road traverses through three districts of Nwoya, Omoro and Gulu. The project scope includes surfacing, earthworks for widening, improvements to alignment geometry and side ditches.
Others works include swamp reclamation, construction of fills and subgrade with natural granular material, construction of new pipe culverts and one bridge. There was a variation in the scope to include 2 (two) 5m x 3m reinforced Box Culvert at Km 7+705 to replace the narrow and dilapidated bridge.
Project Variations
The total contract sum for this project was initially UGX 164,025,932,344. This was, however, later revised downwards to UGX 155,188,105,345, indicating a possible UGX 460 million (0.28%) saving.
Project Progress
The team observed that all the project activities, only the installation of the Box culvert and minor overlays were left by the time of the Monitoring visit.
The team also learnt from that the physical progress achieved as of August 2019 stood at 99.93% as compared to the planned 100% for the main project road (now substantially completed) and 85.4% against programmed 92% for the Gulu Town roads. Time elapsed was 98% as per the revised completion date of 30 July 2019. Financial progress was at 94.80% as of August 2018.
The cumulative amount for the Contractor certified to date is UGX 95,208,729,466 representing 61.35% of the revised UGX 155,188,105,345.
Rehabilitation of Oryang-Ojuma-Kitgum-Matidi Road in Gulu
Project Details |
Information |
Project name and Length |
Rehabilitation of Oryang – Ojuma – Kitgum - Matidi Road, Gulu (16.2km) |
Contractor |
MoWT Force Account |
Supervision consultant |
MoWT |
Contract sum |
UGX 470m |
Funder (s) |
Government of Uganda |
Scope of Works |
Bush Clearing, Grading and Gravelling |
Surfacing |
Gravel |
Commencement date |
April 2019 |
Completion date |
September 2019 |
Contract time elapsed |
83% |
Physical Progress against planned |
90% against 86% |
Amount paid in land compensation |
Nil |
Contractor’s staff |
19 Staff (Male: 18, Female: 1; 19 Local And 0 Foreign) |
Project details
This project is located in Northern Uganda in the district of Kitgum. It is 16.2 km
Project Scope
The scope of work consists of widening the embankment, bush clearing and gravelling.
Project progress
- The work done against progress stands at 11.36% against a planned 43.18% indicating slippage of 31.82% .
- The design progress stands at 86.57% against a planned 100.00% indicating slippage of 13.43% .
- The financial progress is 13.78% against a planned 45.42%.
- The contract time elapsed by the time of the visit was 44%.
Musita-Lumino-Busia-Majanji Road (104km)
Project details
Project Detail |
Information |
Project Title |
Package 4: Upgrading of Musita-Lumino-Busia-Majanji Road (104km) |
Project Funding |
Government of Uganda (GoU): 100% |
Implementing Agency |
Uganda National Road Authority. |
Main Contractor |
China Railway 18th Bureau Group Co Ltd. |
Engineer |
M/s. Consulting Engineering Centre, Jordan in Joint Venture with MBW Consulting Ltd, Uganda Venture |
Works Contract Award Date |
13th June 2014 |
Original Commencement Date |
15 September 2014 |
Supervision Commencement Date |
27 January 2015 |
Original Contract Price |
Original: UGX 206,784,423,053 |
Revised Contract Amount |
UGX.208,983,285,921 (Yet to be approved) |
Original Contract Duration |
Original: 1096 days (36 months) |
Original Completion date |
17th September 2017 |
Contract termination date |
12th June 2017 |
Revised completion date |
18th October 2019 |
Time progress |
19.5 months (88.32%) |
Financial Progress |
80.24% |
Physical Progress |
99% against 95% Planned |
The Musita-Lumino-Busia-Majanji road is a gravel and earth road situated in the eastern part of Uganda. It traverses the Districts of Mayuge, Bugweri (previously Iganga), Bugiri, Namayingo and Busia. It is an alternative route connecting Musita Trading Centre on Jinja-Iganga highway to Busia town on the Uganda-Kenya border through Mayuge District. It is a short cut from Busia border town to Jinja through Namayingo-Nankoma and Musita town. The road serves as a link to a number of landing sites like Majanji, Lugala, Lufudu, Omenya, Wakawaka and Kigandala. It is an easier link to Dorwe, Hama and Sigulu islands.
Scope of works
The works being carried out comprise the Upgrading to a Class II Bitumen Standard of approximately 104 Km of the existing gravel road and approx. 20 Km of town roads. The completed road will have 7.0 m carriageway width flanked by 2.0m or 1.5 m double surface -dressed shoulders. The works include earthworks for widening, improvements to alignment geometry and side ditches, reconstruction of shoulders with natural material, construction of cement stabilized sub base, a base course with crushed stone material and double surface dressing and ancillary works.
The road is comprised of 300mm thick stabilized sub base, 200mm thick CRS base and a double surface dressing with lined drainage channels in urban areas. The road carriageway and shoulder width is 10m in rural areas.
Project progress
99.00% against 95.00% planned i.e. 13.64% at termination (June 2017), plus 3.84% works done before termination but approved after termination plus 81.52 % for the period from January 2018 and up to and including July 2019. The actual monthly progress in the month of July 2019 is estimated at 3.02% against a plan of 3.97% with a monthly slippage/gain of -0.95%.
Mbaale-Lwakhakha-Bumbobi (44km)
Project details
Project Details |
Information |
Project Name: |
Upgrading of Bumbobi- Lwakhakha Road (44.5 km) |
Funding Agency: |
African Development Fund (ADF) and Government of Uganda (GoU). |
Contractor: |
China State Construction Engineering Corporation Ltd of No.15 |
Supervision Consultant: |
SGI Studio Galli Ingegneria Sri in JV with SARI Consulting Ltd, Consulint Sri and AES (Anchor Engineering Services) Ltd |
Implementing Agency: |
Uganda National Roads Authority (UNRA) |
Original project duration: |
24 months (inclusive of 3 months mobilisation period) |
Revised project duration: |
36.8 months (inclusive of 3 months mobilisation period) |
Original contract sum: |
UGX 140,724,306,533.35/= inclusive of all applicable taxes |
Revised contract price: |
UGX 140,722,631,426.39/= inclusive of all applicable taxes |
Commencement date: |
6 December 2016 |
Original completion date: |
6 December 2018 |
Revised completion date: |
31 December 2019 (Recommended to UNRA) |
Physical progress |
65.24% |
Overall time progress: |
88.3% |
Financial progress: |
67.69% |
Scope of Works
The scope of works comprise of the following:
- Bush clearing and road widening
- Sub-grade: 200mm thick improved gravel material where sub-grade is <15% CBR.
- Sub-base: 250mm mechanically modified subbase.
- Base course: 250mm graded crushed stone
- Surfacing: Double Surface Dressing
- Construction of 4 bridges at Manafwa, Namunyiri, Namikhoma & Lwakhakha Border
- Installation of pipe culverts.
Tirinyi-Pallisa-Kumi (67km)
Project details
Project Details |
Information |
Project Name: |
Upgrading from Gravel to Bituminous Standard of Tirinyi-Pallisa-Kumi Road Project |
Funding Agency: |
Government of Uganda (GoU) and Islamic Development Bank |
Contractor: |
The Arab Contractors (Osman Ahmed Osman & Co) |
Supervision Consultant: |
Construction and Supervision Unit -UNRA |
Implementing Agency: |
Uganda National Roads Authority |
Contract duration: |
36 Months |
Contract sum: |
274,124,619,957.01 |
Commencement date: |
15th March 2018 |
Expected completion date: |
15th March 2021 |
Overall physical progress: |
27.00% against 29.35% |
Overall time progress: |
534 days (48.79%) |
Financial progress: |
33.73% against 34.65% (as extracted from S-Curve August 2019) |
Project progress
The contractor is undertaking earthworks from CH 19+630-CH 55+500, mostly doing clearing and grubbing, removal of topsoil, roadbed preparation, common excavation swamp improvement, fills, subgrade and sub-base processing. Swamp treatment, gabion and culvert construction at km 41+000-41+980 and km15+100-15+900 is ongoing. Subgrade, subbase and base layer construction is also ongoing from Km 24+780-Km 41+000 with exception of seasonal swamps. The contractor has also started the construction of the Asphalt layer after doing a trial from km35+050 to km 35+100.