Project Details |
Information |
Project name and Length |
Rehabilitation of Oryang – Ojuma – Kitgum - Matidi Road, Gulu (16.2km) |
Contractor |
MoWT Force Account |
Supervision consultant |
MoWT |
Contract sum |
UGX 470m |
Funder (s) |
Government of Uganda |
Scope of Works |
Bush Clearing, Grading and Gravelling |
Surfacing |
Gravel |
Commencement date |
April 2019 |
Completion date |
September 2019 |
Contract time elapsed |
83% |
Physical Progress against planned |
90% against 86% |
Amount paid in land compensation |
Nil |
Contractor’s staff |
19 Staff (Male: 18, Female: 1; 19 Local And 0 Foreign) |
Project details
This project is located in Northern Uganda in the district of Kitgum. It is 16.2 km
Project Scope
The scope of work consists of widening the embankment, bush clearing and gravelling.
Project progress
- The work done against progress stands at 11.36% against a planned 43.18% indicating slippage of 31.82% .
- The design progress stands at 86.57% against a planned 100.00% indicating slippage of 13.43% .
- The financial progress is 13.78% against a planned 45.42%.
- The contract time elapsed by the time of the visit was 44%.