Project Details |
Information |
Project name and Length |
Civil Works for Design and Build for Upgrading from Gravel to Paved Standard of Masindi (Kisanja) - Park Junction and Tangi Junction - Paraa - Buliisa (159 Km) |
Contractor |
China Communications Construction Company Ltd. (CCCC) |
Supervision consultant |
Abuljebain Engineering Consulting Office (AECO) in association with Technology Consult Ltd |
Contract sum |
USD 218,888,518.4 |
Funder (s) |
China Exim Bank and Government of Uganda |
Scope of Works |
Design and Build Contract |
Surfacing |
Asphalt Concrete |
Commencement date |
23rd April 2018 |
Completion date |
26th April 2021 |
Contract time elapsed |
44.22% |
Physical Progress |
11.36% against 43.18% |
Design Progress |
86.57% against the planned 100.00% |
Contractor’s staff |
822 Staff (Male: 756, Female: 66; 671 Local, 151 Foreign) |
Supervisor’s staff |
27 Staff (21 Males, 6 Females; 26 Local, 1 Foreign) |
Project details
This project is located in Western Uganda and crosses the districts of Masindi, Nwoya and Buliisa. The road traverses a flat/rolling terrain and it involves upgrade of the road to bituminous paved road. The project consists of four lots namely;
- Masindi – Kisanja (72 km)
- Sambiya – Murchison Falls (12 km)
- Tangi Junction – Paraa – Buliisa (52 km)
- Wanseko – Bugungu (23 km)
Project Scope
The scope of work consists of:
- Widening the embankment, bush clearing and topsoil stripping. The lower subgrade is made of G7 fill materials of 250-350 mm and the improved subgrade of G15 125-350mm. The subbase will be chemically stabilized cement of 150-215 mm, 125-150 mm of crushed stone base course and a wearing course of Asphalt Concrete of 55-100mm.
- Installation of concrete pipe culverts of 900 mm and 1200mm and construction of single and multiple cell box culverts.
- Construction of a total of 7 bridges along the road, and these include four (4) along Masindi – Kisanja section namely; Waiga with a span of 24m, Wairongo with a span of 30m, Zoliya with a span of 18m, and Sambiya with a span of 18m.
Three (3) bridges are on Tangi Junction – Paraa – Buliisa section namely; Tangi with a span of 30m, Emmi with a span of 18m and a big Paraa Bridge with a span of 525m.
- Paraa bridge, which is composed of 13 spans each at 40m and bridge deck of 15.95m wide.
Project progress
- The work done against progress stands at 11.36% against a planned 43.18% indicating slippage of 31.82%.
- The design progress stands at 86.57% against a planned 100.00% indicating slippage of 13.43%.
- The financial progress is 13.78% against a planned 45.42%.
- The contract time elapsed by the time of the visit was 44%.
- Works on the bridges stands at Waiga 39.67%, Wairongo 54.10%, Zoliya 43.05%, Sambiya 22.76%, Tangi the designs had just been approved, Emmi 18.17% and Paraa Bridge 9.55% and a temporary steel bridge had been completed and use.