Project details
Project Details |
Information |
Project Name: |
Upgrading of Bumbobi- Lwakhakha Road (44.5 km) |
Funding Agency: |
African Development Fund (ADF) and Government of Uganda (GoU). |
Contractor: |
China State Construction Engineering Corporation Ltd of No.15 |
Supervision Consultant: |
SGI Studio Galli Ingegneria Sri in JV with SARI Consulting Ltd, Consulint Sri and AES (Anchor Engineering Services) Ltd |
Implementing Agency: |
Uganda National Roads Authority (UNRA) |
Original project duration: |
24 months (inclusive of 3 months mobilisation period) |
Revised project duration: |
36.8 months (inclusive of 3 months mobilisation period) |
Original contract sum: |
UGX 140,724,306,533.35/= inclusive of all applicable taxes |
Revised contract price: |
UGX 140,722,631,426.39/= inclusive of all applicable taxes |
Commencement date: |
6 December 2016 |
Original completion date: |
6 December 2018 |
Revised completion date: |
31 December 2019 (Recommended to UNRA) |
Physical progress |
65.24% |
Overall time progress: |
88.3% |
Financial progress: |
67.69% |
Scope of Works
The scope of works comprise of the following:
- Bush clearing and road widening
- Sub-grade: 200mm thick improved gravel material where sub-grade is <15% CBR.
- Sub-base: 250mm mechanically modified subbase.
- Base course: 250mm graded crushed stone
- Surfacing: Double Surface Dressing
- Construction of 4 bridges at Manafwa, Namunyiri, Namikhoma & Lwakhakha Border
- Installation of pipe culverts.