USMID Roads in Gulu

Project details

The objective of the Uganda Support to Municipal Infrastructure Development Program Project (USMID) is to enhance the institutional performance of program Municipal Councils (MCs) to improve urban service delivery.

The program will also involve a range of administration, oversight and support activities to be undertaken by the relevant central government entities responsible for the various elements of the implementation of the Program. The main aim of the program is to enhance the capacity of the targeted municipalities to improve urban service delivery in the context of a rapidly urbanizing society in which significant service delivery responsibilities have been decentralized.

The Overall Program Objective is to enhance the institutional performance of the 14 Municipal Councils to improve urban service delivery. The participating Municipal Councils (MCs) are; Arua, Lira, Gulu, Soroti, Entebbe, Mbale, Tororo, Jinja, Masaka, Hoima, Fort portal, Mbarara, Kabale and Moroto.

Under the entire USMID project, Infrastructure construction provided direct employment to 2,716 people of which 442 were female representing 16.3% of the entire workforce. The project has also improved 66,113 square meters of green area and planted 2,407 trees.

The Project

Gulu Municipality as one of the 14 recipients of the infrastructure development grant under the World Bank funded Uganda Support to Municipal Infrastructure Development (USMID). It is believed that through this improved road network, transacting business with neighboring districts as well as South Sudan will greatly improve thus leading to transformation of livelihoods.

The project requires upgrading the roads from gravel surface road to an Asphalt surface layer of 50mm, with base course and sub-base layers. A carriage way of 7 m total width with two lanes in opposite direction, a parking lane each side, a cycle lane on each side, 1.5m walkways on each side of the road, street lights, service ducts and drains. Gulu has since rehabilitated and tarmacked roads that include:

Completed USMID Projects Phase 1A

S/No

Road Name

Length (km)

Lanes

1

Labor Line Road

0.331

2

2

Cemetery Road

0.408

2

3

Acholi Lane

0.608

2

4

Alokolum Road

0.651

2

5

Ring Road

1.64

4

TOTAL

3.638

 

Completed USMID Projects Phase 1B

S/No

Road Name

Distance (Km)

Lanes

01

Kabalega Road

0.160

2

02

Adonga Road

0.334

2

03

Crane Avenue

0.195

2

04

Philip  Tarner

0.266

2

05

Odur Min Odyek Rd

0.336

2

06

Commercial road

0.364

2

07

School Road

0.355

2

08

Salvatore Olwochi Road

0.672

2

09

Oponya Walter Road

0.670

4

10

Muroni  Road

0.694

2

11

Lumumba Avenue

0.250

4

12

Lango Road

0.226

2

TOTAL

4.522

 

BATCH II 2017-2018  

S/No 

Activity Name

Distance (km)

Lanes

01

Preliminaries

   

02

Laroo road

2.46

2

03

Alex  Ojera road

0.680

2

04

Tank road

0.340

2

05

Dr. Kenneth Onekalit road

0.270

2

06

Lasto Okech road

0.500

2

07

Golf-Course road

0.450

2

08

Nyerere Avenue

0.880

2

09

Odida road

0.250

2

10

Timothy Okwera road

0.420

2

11

Peter Paul Opok road

0.860

2

12

Bro. Reuben road

0.640

2

13

Sir Samuel Baker road

1.280

2

14

Hussan Mitchel road

0.540

2

 

TOTAL

9.37