Low Cost Sealing of Kyerima-Nakaseeta-Lukonda Road

Section A: Kyerima-Nakaseeta- Lukonda (6.0km) in Kayunga District

Project details

Project Details

Information

Project Name:

Nakaseeta- Lukonda Road Section A (6.0km)

Funding Agency:

Government of Uganda (GoU)

Contractor:

M/S Empa Associates Ltd

Supervision Consultant:

Ministry of Works and Transport

Contract sum:

6.403 Bn

Commencement date:

15th February 2019

Completion date:

22nd August 2019, revised to 21st October 2019

Physical progress

35%

Time progress:

71%.

 

The Low cost sealing of Kyerima-Nakaseeta-Lukonda road section A (6.0 km) located in Kayunga District was contracted out to M/S Empa Associates Ltd.  The project commenced and work is ongoing.

Scope of work

The scope consists of Site preparatory works, setting out and clearance works, Earth works, Drainage/structural works, Gravelling, completion works and surfacing works using Low Cost Sealing technology (single surface dressing with quarry dust cupping option).

Project progress to-date

Physical Progress:

  • The Site preparatory works, setting out, clearance works, sub-grade preparation and sub base construction have been completed.
  • Earth works, base and Drainage/structural works is ongoing.

The overall work progress stands at 35% against a time progress of 71%.

 

Section B: Kyerima-Nakaseeta-Lukonda (6.0km) in Kayunga District

Project details

Project Details

Information

Project Name:

Kyerima- Nakaseeta-Lukonda Road Section B (6.0km)

Funding Agency:

Government of Uganda (GoU)

Contractor:

M/S Bestways General Contractors Ltd

Supervision Consultant:

Ministry of Works and Transport

Original contract sum:

Shs 3,405,337,662/=

Commencement date:

15th February 2019

Completion date:

22nd August 2019, revised to 21st October 2019

Physical progress

30%

Time progress:

96%.

Financial progress:

20%

The Low cost sealing of Kyerima-Nakaseeta-Lukonda road section B (6.0 km) was contracted out to M/s. Bestways General Contractors Ltd.  The project commenced and work is ongoing.

Scope of work

The scope consists of Site preparatory works, setting out and clearance works, Earth works, Drainage/structural works, Gravelling, completion works and surfacing works using Low Cost Sealing technology (single surface dressing with quarry dust cupping option).

 

 

Project progress to-date

Physical Progress:

  • The Site preparatory works, setting out, clearance works, sub-grade preparation and sub base construction have been completed.
  • Drainage works are ongoing.

The overall work progress stands at 30% against a time progress of 96%.