Section A: Kyerima-Nakaseeta- Lukonda (6.0km) in Kayunga District
Project details
Project Details |
Information |
Project Name: |
Nakaseeta- Lukonda Road Section A (6.0km) |
Funding Agency: |
Government of Uganda (GoU) |
Contractor: |
M/S Empa Associates Ltd |
Supervision Consultant: |
Ministry of Works and Transport |
Contract sum: |
6.403 Bn |
Commencement date: |
15th February 2019 |
Completion date: |
22nd August 2019, revised to 21st October 2019 |
Physical progress |
35% |
Time progress: |
71%. |
The Low cost sealing of Kyerima-Nakaseeta-Lukonda road section A (6.0 km) located in Kayunga District was contracted out to M/S Empa Associates Ltd. The project commenced and work is ongoing.
Scope of work
The scope consists of Site preparatory works, setting out and clearance works, Earth works, Drainage/structural works, Gravelling, completion works and surfacing works using Low Cost Sealing technology (single surface dressing with quarry dust cupping option).
Project progress to-date
Physical Progress:
- The Site preparatory works, setting out, clearance works, sub-grade preparation and sub base construction have been completed.
- Earth works, base and Drainage/structural works is ongoing.
The overall work progress stands at 35% against a time progress of 71%.
Section B: Kyerima-Nakaseeta-Lukonda (6.0km) in Kayunga District
Project details
Project Details |
Information |
Project Name: |
Kyerima- Nakaseeta-Lukonda Road Section B (6.0km) |
Funding Agency: |
Government of Uganda (GoU) |
Contractor: |
M/S Bestways General Contractors Ltd |
Supervision Consultant: |
Ministry of Works and Transport |
Original contract sum: |
Shs 3,405,337,662/= |
Commencement date: |
15th February 2019 |
Completion date: |
22nd August 2019, revised to 21st October 2019 |
Physical progress |
30% |
Time progress: |
96%. |
Financial progress: |
20% |
The Low cost sealing of Kyerima-Nakaseeta-Lukonda road section B (6.0 km) was contracted out to M/s. Bestways General Contractors Ltd. The project commenced and work is ongoing.
Scope of work
The scope consists of Site preparatory works, setting out and clearance works, Earth works, Drainage/structural works, Gravelling, completion works and surfacing works using Low Cost Sealing technology (single surface dressing with quarry dust cupping option).
Project progress to-date
Physical Progress:
- The Site preparatory works, setting out, clearance works, sub-grade preparation and sub base construction have been completed.
- Drainage works are ongoing.
The overall work progress stands at 30% against a time progress of 96%.