Project details
Project Details |
Information |
Project Name: |
Reconstruction and Upgrading of Kulekana Rd-1.95km, Nsambya-Katwe – 0.60km, Jjuko – 1.26km, Kevina – 1.18km, Appas – 1.32km, and Bugolobi-Namuwongo Link – 0.4km. |
Funding Agency: |
Government of Uganda |
Contractor: |
M/s. Abubaker Technical Services Ltd |
Supervision Consultant: |
UB Consulting Engineers Ltd. P. O. Box 22509 Kampala. |
Implementing Agency: |
Kampala Capital City Authority (KCCA) |
Original Project duration: |
18 months |
Original contract sum: |
UGX.31,573,958,587 |
Revised contract price: |
UGX.36,008,050,621 |
Commencement date: |
20th June 2016 |
Completion date: |
20th December 2017, revised to 20th June 2020 |
Physical progress (Aug. 2019) |
68% |
Overall time progress: |
77% |
Overall Financial progress: |
60.5% |
Reconstruction of Lukuli Road
Project Details |
Information |
Project Name: |
Reconstruction of Lukuli Road (7.71km) |
Funding Agency: |
Government of Uganda |
Contractor: |
Joint Venture between Stirling and SOBETRA |
Supervision Consultant: |
|
Implementing Agency: |
Kampala Capital City Authority (KCCA) |
Project duration: |
15 months |
Contract sum: |
UGX.68 bn |
Commencement date: |
May 2019 |
Expected completion date: |
August 2020 |
- The 7.71 km road project starts from Hass Petrol Station and connects to Salama Road;
- The project works involve expansion of the road width from the current 5 – 6 metres to 7 metres, with 1.5 metre walk-ways on either side of the road;
- Street lighting is part of the contract;
- At the time of inspection, the contractor had completed all the necessary preparations, and had started on the physical works;
- There will be no compensation of Project Affected People (PAPs).