Ongoing Road Projects in Makindye Division

Project details

Project Details

Information

Project Name:

Reconstruction and Upgrading of Kulekana Rd-1.95km,  Nsambya-Katwe – 0.60km, Jjuko – 1.26km, Kevina – 1.18km, Appas – 1.32km, and Bugolobi-Namuwongo Link – 0.4km.

Funding Agency:

Government of Uganda

Contractor:

M/s. Abubaker Technical Services Ltd

Supervision Consultant:

UB Consulting Engineers Ltd. P. O. Box 22509 Kampala.

Implementing Agency:

Kampala Capital City Authority (KCCA)

Original Project duration:

18 months

Original contract sum:

UGX.31,573,958,587

Revised contract price:

UGX.36,008,050,621

Commencement date:

20th June 2016

Completion date:

20th December 2017, revised to 20th June 2020

Physical progress (Aug. 2019)

68%

Overall time progress:

77%

Overall Financial progress:

60.5%

 

 

Reconstruction of Lukuli Road

Project Details

Information

Project Name:

Reconstruction of Lukuli Road (7.71km)

Funding Agency:

Government of Uganda

Contractor:

Joint Venture between Stirling and SOBETRA

Supervision Consultant:

Implementing Agency:

Kampala Capital City Authority (KCCA)

Project duration:

15 months

Contract sum:

UGX.68 bn

Commencement date:

May 2019

Expected completion date:

August 2020

 

  • The 7.71 km road project starts from Hass Petrol Station and connects to Salama Road;
  • The project works involve expansion of the road width from the current 5 – 6 metres to 7 metres, with 1.5 metre walk-ways on either side of the road;
  • Street lighting is part of the contract;
  • At the time of inspection, the contractor had completed all the necessary preparations, and had started on the physical works;
  • There will be no compensation of Project Affected People (PAPs).