Project detail |
Information |
Project Title: |
Development of Kabaale International Airport, Uganda |
Funded by: |
The Project is financed 85% by UKEF and 15% by commercial source-Standard Chartered Bank |
Contractor: |
SBC (Uganda) Ltd, Joint venture of SBI International Holdings AG and Colas, UK |
Original Contract Price: |
Total Value of the Contract EUR 309,100,259 of which 264,077,144 is for Construction |
Commencement date: |
18th April 2018 |
Construction period: |
58 months |
Work done to date: |
27.65% of Actual Progress of Works complete |
Project details
Development of Kabaale /Hoima International Airport in Hoima, Uganda is being undertaken by SBC (Uganda) Ltd, a joint venture of SBI International Holdings AG and Colas, UK. The Project is financed 85% by UK Export Finance (UKEF) and 15% by Commercial Source-Standard Chartered bank. The value of the Contract is €309,100,256 of which €264,077,144 is for Construction.
Scope of works
The project consists of the following scope of works
- Runway 3,500 m length, 45 m width with shoulders of 15 m each side
- Platform of 75,000 m2 ready to receive 4 Antonov’s 124 or Boeing 747-8
- Cargo terminal
- Airport Rescue and Firefighting Building
- Accommodation block with 30 double two-bedroom houses and 6 single three bedroom houses
- Fuel farm
- Airport Ground Lights
- Mobile Air Traffic Control Tower
- Access roads and parking
- Power and Water Supply
The actual physical progress of works is 27.65% complete against the planned progress of works 27.3%. The period of time elapsed stands at 26.6%. Overall completion of current project activities is 27.65% (Financial) as of July 2019.
Current status
Activity |
% Completion |
Mobilization |
100 |
Bush Clearing at airport site |
99.7 |
Topsoil stripping at airport |
99.7 |
Fencing of Airport Project Area |
100 |
Road Diversion Works at KM 3+900 |
100 |
Rock Fill at Swamp Areas |
100 |
Box Culvert at KM 4+500 |
06 |
Access Road Tarmacking |
20.5 |
Cut off Drains |
3.2 |
Air strip Earthworks · Cut to Fill · Bulk Fill · Road Bed · Capping Layer · Subbase · Base |
46 47 28 13.3 11.3 5.7 |
Geotechnical Investigations |
100 |
Other on-going activities include:
- Quarry – Pit Preparation, Drilling, Blasting and Crushing
- Drainage, Erosion & Effluent control structures in Main Site & Quarry & Construction Zone
- Health & Safety and Environment & Social Monitoring of Project and Project footprint area.