Project details
Project Details |
Information |
Project Name: |
NMT Pilot Corridor – 1.5km |
Funding Agency: |
Government of Uganda |
Contractor: |
M/s. Stirling |
Implementing Agency: |
Kampala Capital City Authority (KCCA) |
Contract duration: |
15 months |
Contract sum: |
UGX.3.5 Bn |
Commencement date: |
June 2018 |
Expected completion date: |
30th August 2019, revised to 30th November 2019 |
Overall physical progress: |
39% |
The project is a design and build contract being undertaken by M/s. Stirling. It covers a distance of 1.5 km from Bakuli to Luwum Street. Although the initial concept was having an entire road designed as non-motorized, some sections of the road will be motorized. This is because there are already existing businesses, e.g. shops, and the owners would need vehicles to come close to their premises, e.g. delivery trucks.