Water

Kabindula Swamp Crossing

Project Details

Information

Project name and Length

Construction of Kabindula Swamp Crossing (180M )

Contractor

Ms. Shataman Contractors Uganda Ltd

Contract sum

Original Contract: UGX 1,245,084,434

Funder (s)

Government of Uganda

Districts traversed by project

Kyankwazi

Commencement date

18th July 2018

Completion date

Initial completion: 30th April 2019

Revised completion : 30th August 2019

Work done to date (%) against the program

60% against 71.88% of planned

Supervision Consultant

Ministry of Works and Transport

Supervision commencement date

18th July, 2018

 

 

Project Location

Kabindula Swamp Crossing is located along Ntwetwe – Kitwala Road across River Kitumbi on the District Road Network. The swamp crossing is approximately 180m long, with River Kitumbi marked at the centre.

During inspection, it was observed that the crossing comprised of pipe culverts at these approximate chainages: 5x1200mm diameter concrete culverts at 0+210 and 0+150; 7×1200 mm at 0+180. Most of the culverts were flowing full due to being blocked by silt and also as a result of being laid at very low inverts.

Upon drainage analysis and geotechnical studies, structures were proposed and adopted as the design intervention. It’s upon these findings that the Ministry decided to reconstruct the bridge. A contract agreement was therefore signed on 5th June, 2018 between the Ministry of Works and Transport and M/s. Shataman Contractors (U) Ltd for the construction of Kabindula Swamp crossing in Kyankwanzi District.

 

Progress

Actual physical works as of July 2019 was at 75% against a planned 100%. Initial project completion date was 30th April 2019, but the project was extended at no cost to 30th August 2019 due to inclement weather which halted works.

Laropi & Obongi Ferry

Project details

Laropi is a marine vessel that connects Adjumani District to Moyo District. It connects the landing sites of Laropi and Umi.

The ferry starts operations at 5:30am and often ends at by 7pm. It has a vessel capacity of 120 tonnes.

It carries an average of 1,500 to 1,800 people per day at the crossing with a minimum of 12 trips and a maximum of 22 trips. It takes 30 minutes for loading and offloading while the time to cross is between 10 to 15 minutes.

The ferry has a capacity of 180 passengers and cargo of 90 tonnes as per the Certificate of Sea Worthiness.

To provide for maintenance of the ferry, usually the team reserves half a day for routine maintenance or conduct one after the end of day route operations.

 

Project progress

The Laropi Ferry had barely served for a year and was expected to ease the movement of people in Adjumani and Moyo areas.

 

Staffing and gender issues

The Laropi Ferry has twenty-six (26) staff. These include 10 UNRA staff (1 Ferry Master, 3 Operators, 2 Mechanics, 4 Ferry Attendants), 10 Uganda Police Force staff and 6 support staff. Four (4) of the support staff are females representing 15 % of the total.

Each trip consists of 3 staff that help with the navigation of the ferry and 2 staff for watch keeping.

 

Observations

The facilities at the landing site at Laropi included 2 waiting sheds, 1 office block and a washroom while the landing site at Umi included 2 waiting sheds and a washroom which was faulty and needed repairs however the locals at the landing site have made it impossible to repair the washrooms due to an ongoing land wrangle. UNRA mentioned that there is an ongoing engagement on the matter.

Access roads to the ferry were in a good condition and there was a clear route schedule visible at both sides of the crossing.

There was a clear demand of the services of the ferry and the Ferry master observed that there had been demands by the passengers for the increase of the ferry operational hours to 10 PM to satisfy the business hours of the local community however this poses a risk to the ferry operators as the ferry is not designed for navigation in the dark.

 

Safety and security measures

The ferry is insured for passengers and Cargo until 15th August 2020. The ferry has life jackets (235 for adults and 40 for children), 5 ring buoys, 4 sand buckets, a hose, and 8 fire extinguishers (6 onboard and 2 at the operational inputs stores).

There was presence of Aids to navigation in place and they included; ferry lights, an onboard Public Address System, and a reflective signage at Laropi.

There was mandatory passenger registration and screening handled by the Uganda Police, security checks for both passengers, vehicles and luggage before going to the ferry. The Passenger and Cargo manifests were maintained properly.

Kangai Swamp Crossing (Dokolo District)

Project details

The site is 17km from Dokolo Local Government Headquarters and 7km from Kaberamaido town. It borders Kaberamaido and Dokolo Districts linking Kabalega market, Kangai Sub-County and Oyama Sub-County in Kaberamaido District. The Stream empties into the Lake Kyoga Basin.

The Ministry of Works and Transport is undertaking the construction of Kangai Swamp Crossing using Force Account. Works commenced in October 2018 by opening, shaping and gravelling approach roads to allow access to swamp.

The swamp is approximately 400m wide with about 19 lines of culverts which are now and inadequate to accommodate the current hydrological capacity and has led to continuous flooding.

 

Scope of Works

The scope of work consists of construction of a Cofferdam; Construction of river diversion and culvert installation; Earth works/fills at the abutment and wing walls; River training; Installation of roads furniture; and Quality control management.

 

Project progress

The approach road works to the swamp from Kangai equivalent to 1 Km were rehabilitated to facilitate easy access of materials to site. Dredging work intended to enlarge the swamp from current 3.5m carriage way to 7.5m and 10m well stabilized rock base fill was done.

 

Physical Progress

The activities that have been completed include the construction of approach road from Kangai town to the swamp; dredging works along the swamp crossing; Rock base stabilization; and Gravel fills to level the road sections.

On-going activities include assembling of culverts for installation; gravel dumping to increase the vertical and horizontal road sections, and Construction of cofferdam.

The overall works were estimated to cost UGX 700m. Financial progress is 55.2% against a planned progress of 60%.

MV Sigulu

Project details

Sigulu Ferry is in the advanced stages of construction to serve Namayingo district by connecting the Namayingo mainland to Sigulu Island and Lolwe Island on Lake Victoria. The landing sites where the ferry will dock are being developed accordingly. This ferry will provide a safe means for the communities to travel at costs met by the Government. Overall, the project will positively impact the communities through increased volumes of trade, tourism, increased access to social services especially those, which are lacking or inadequate in the islands.

 

Project progress

The project cost is US 4.3 million and the contractor M/S Johs. Gram-Hanssen AlS (JGH) - Western Marine Shipyard Limited Joint Venture has implemented the project up to 98% completion. The key features of this ferry are the hull, propulsion systems, wheelhouse, sheltered passenger seating areas, crew rest room, medical room and cafeteria.

The contractor has finalized most of the painting works, installation of electrical, propulsion and navigation equipment. The Ferry was floated on water, end of June 2019 and the two-week familiarization training immediately commenced. During the training, testing and sea trials were also conducted. Ministry of works and Transport carried out a seaworthiness inspection of the ferry on 25th July 2019. The ferry capacity is 300 passengers and it is currently the biggest Ugandan passenger inland vessel.